Ground-mounted guyed tower
2025-08-13
A tall steel structure composed of columns and guy wires, primarily constructed using steel columns formed from structural steel, with multiple sets of guy wires installed around the perimeter to provide balance, reinforcement, and stability.
Non-self-supporting tower; the tower body cannot independently bear loads and must be supplemented with tie rods to resist external loads. Pre-tensioning of the guy wires during construction provides the tower with rigidity.
Applicable Wind Pressure
Design wind pressure is determined according to load standards.
Applicable Height
20m–30m
Advantages&Disadvantages
Cost-effective; lightweight components, easy to install; few components, bolted connections, can be relocated and reused.
Large footprint; weak load-bearing capacity; low reliability; difficult to install and maintain guy wires; high requirements for anchor points; many components and joints, difficult to relocate and reuse.
Application Scenarios
Suitable for open mountainous areas, rural areas, and other regions with low landscape requirements.
Construction Period
Tower body installation: 1–3 days; foundation construction: 25–30 days
Foundation Types
Depending on geological conditions, the main foundation types for guyed tower guyed foundations include: anchor plate foundations, rock anchor rod foundations; the main foundation types for tower bodies include: independent foundations, pile foundations, etc.